Iift 2012 Question 34
This is a detailed step-by-step solution for Iift 2012 Question 34. Understand the concept, common mistakes, and expert tips to solve similar questions in IIFT exam.
IIFT 2012
Explanation:
12 men can complete a work in ten days. Thus, 1 men will take 120 days.
In 1 day 1 men will complete 1/120 of the work.
20 women can complete the same work in twelve days.
Thus, 1 women will take 240 days to complete the work.
Thus, In 1 day 1 women will complete 1/240 of the work.
8 men and 4 women work for 9 days completing 3/4 of the work.
Thus, of the work is remaining.
Now 8 men and 14 women work completing 1/8 of the work in 1 day.
To complete they'll take 2 days.
Hence, option A is the correct answer.